Project Desription:
Full reconstruction of the footways below addressed sites. Taking up exist paving and dispose. New sub-base material placed at necessary areas. New artificial stone paving slabs are provided and laid on a new sand and cement bed. New recesses covers are adjusted according to new paving level
Year 2005 paving work in City of Westminster area:
1. Warwick Avenue
2. Moxon Street
3. Upper Montegu Place
4. Ebury Street
5. Wilton Street
6. Page Steet
7. Greencoat Place
8. Mannette Street
9. Princes Square
10. Duke of York Street
11. Well Street
12. Newman Street
13. Northumberland Avenue
14. Kinnerton Street
15. Brendon Street
16. Beethoven Street
17. Newbond Street
18. Crawen Street
19. Great Newport Street |