Steatham Drive through Destination – Phase I & II:
    Location:  Streatham High Road, London SW16
    Client:      TFL - McNicholas plc
    Dates:     

    October 2003 – November 2004

    Value:      £ 768,000

    Project:

    Reconstruction of footway areas using Artificial Stone and Yorkstone paving and tactile paved crossings, Construction of kerbs to the standard height.

    New ducts were installed crossing to islands, on island and on footway for traffic lights and electrical street furniture. New drawpits were placed on footway and islands.

    Removing and replacing guardrails and bollards. Traffic management for establishment of vehicle/pedestrian diversions for the duration of the works, in accordance with the design

 